DigiVFX |
![]() |
Digital Visual Effects, Spring 2011
|
Jump to...
project #1
|
AssignmentsPlease note that you have a total of 10 delay days for assignments for the whole semester. After that, points will be deducted. In addition, late assignments might not be included for artifacts voting.project #1: High dynamic range imagingAssigned: 2011/3/10Due: 11:59pm 2011/3/29 handout, submission, voting, artifacts, winning artifacts project #2: Image stitchingAssigned: 2011/3/30checkpoint: 2011/4/17 11:59pm Due: 2011/4/26 11:59pm handout, submission, voting, artifacts, winning artifacts project #3: MatchMoveAssigned: 2011/4/27Due: 2011/5/17 11:59pm handout, TA slides, submission, voting, artifacts, winning artifacts final projectAssigned: 2011/5/18Proposal: 2011/5/31 Due: 2011/6/29 handout, signup |
|||||||
![]() |
![]() |